[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106892":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106892,782,1,"单选题","下列属于正在实施的工作，可反馈更新的参数的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际开始日期与实际完成日期",false,{"key":16,"text":17,"correct":18},"B","完成百分比或尚需工期",true,{"key":20,"text":21,"correct":14},"C","实际使用资源数量\u002F费用",{"key":23,"text":24,"correct":14},"D","实际其他费用和尚需其他费用","本题考查的是OraclePrimaveraP6软件。对于正在实施的工作，可反馈更新的参数主要包括：实际开始日期，完成百分比或尚需工期，实际常规数量\u002F费用和尚需数量\u002F费用，实际其他费用和尚需其他费用。更新时应按照新的开始日期进行计算。选项ACD属于对于已实际完成的工作，可反馈更新的参数。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]