[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106890":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106890,782,1,"单选题","计算工期延长的方法中，在明确了干扰事件对各项工作作业时间的影响后，（ ）适用于各种干扰事件的索赔计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","平衡点法",false,{"key":16,"text":17,"correct":18},"B","网络计划分析法",true,{"key":20,"text":21,"correct":14},"C","比例法",{"key":23,"text":24,"correct":14},"D","类比法","在实际工作中，计算工期延长的方法有平衡点法、比例法、网络计划分析法等。推荐采用网络计划分析法，其概念清晰，计算准确，优势明显。网络计划分析法计算工期延长是一种科学的、合理的分析方法。在明确了干扰事件对各项工作作业时间的影响后，网络计划分析法适用于各种干扰事件的索赔计算。网络计划分析法基本思路为：在执行原网络计划的施工过程中，若发生了一个或一些干扰事件，使网络中的某个或某些工作受到干扰而延长持续时间。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]