[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106889":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106889,782,1,"单选题","由于（ ）的原因，导致工期拖延，从而增大了工程成本时，承包人有权申请工期延误事件引起的派生费用损失。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不可抗力",false,{"key":16,"text":17,"correct":14},"B","法律条文改变",{"key":19,"text":20,"correct":21},"C","发包人方面",true,{"key":23,"text":24,"correct":14},"D","季节性大雨","本题考查的是工期延误的计算。由于发包人方面的原因，导致工期拖延，从而增大了工程成本时，承包人有权在获得工期延长补偿以外，申请工期延误事件引起的派生费用损失。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]