[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106888":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106888,782,1,"单选题","在施工实践中，经常由于（ ）的发生引起进度计划的调整，从而引起施工设备使用发生冲突或闲置。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","资源分配的调整",false,{"key":16,"text":17,"correct":14},"B","施工进度计划的调整",{"key":19,"text":20,"correct":21},"C","施工进度延误事件",true,{"key":23,"text":24,"correct":14},"D","资金分配的调整","本题考查的是期延误派生费用分析。在施工实践中，经常由于施工进度延误事件的发生引起进度计划的调整，从而引起施工设备使用发生冲突或闲置。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]