[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106887":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106887,782,1,"单选题","工程工期延长应等于该工作作业时间的延长减去其（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作自由时差",false,{"key":16,"text":17,"correct":18},"B","工作总时差",true,{"key":20,"text":21,"correct":14},"C","工作原计划时长",{"key":23,"text":24,"correct":14},"D","工作工期","本题考查的是工期延误的计算。工程工期延长应等于该工作作业时间的延长减去其工作总时差。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]