[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106886":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106886,782,1,"单选题","监理人确定追加的付款和（或）延长的工期，并在收到索赔通知书或有关索赔的进一步证明材料后的（ ）天内，将索赔处理结果答复承包人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","42",true,{"key":16,"text":17,"correct":18},"B","40",false,{"key":20,"text":21,"correct":18},"C","30",{"key":23,"text":24,"correct":18},"D","10","监理人收到承包人提交的索赔通知书后，应及时审查索赔通知书的内容、查验承包人的记录和证明材料，必要时监理人可要求承包人提交全部原始记录。监理人应商定或确定追加的付款和（或）延长的工期，并在收到索赔通知书或有关索赔的进一步证明材料后的42天内，将索赔处理结果答复承包人。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]