[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106885":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106885,782,1,"单选题","常用的实际进度与计划进度对比的方法是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","横道图",false,{"key":16,"text":17,"correct":14},"B","列表检查法",{"key":19,"text":20,"correct":14},"C","割切检查法",{"key":22,"text":23,"correct":24},"D","标图检查法",true,"A项，横道图检查施工进度具有简单、直观的特点，工程进度曲线具有进度的综合、概括等特点，将横道图与工程进度曲线结合进行时度检查、分析，从中可以清楚地了解各项工作的目标进度和实际进度，实践应用效果很好；B项，列表检查法是将检查结果列表分析比较，也是一种常用的进度检查方法；C项，割切检查法是一种将网络计划中已完成部分割切去，然后对剩余网络部分进行分析的一种方法；D项，标图检查法是一种常用的实际进度与计划进度对比的方法，简单且实用。具体方法是：将所查时段内完成的工作项目用图或文字及时地标注到进度计划图（网络图、横道图或形象进度图）上，并随时加以分析。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]