[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106882":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106882,782,1,"单选题","时标图上箭线长度与其工程实物量的多少成（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","反比",false,{"key":16,"text":17,"correct":14},"B","倍数",{"key":19,"text":20,"correct":21},"C","正比",true,{"key":23,"text":24,"correct":14},"D","对应关系","本题考查的是施工进度的动态分析与调整。时标图上箭线长度与相应工作的持续时间对应，也与其工程实物量的多少成正比。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]