[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106881":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106881,782,1,"单选题","割切检查法的步骤描述正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","把检查之后的日期作为剩余网络计划的开始日期",false,{"key":16,"text":17,"correct":18},"B","去掉已经完成的工作，对剩余工作组成的网络计划进行分析",true,{"key":20,"text":21,"correct":14},"C","若产生正时差，则说明项目进度拖后",{"key":23,"text":24,"correct":14},"D","应在出现正时差的工作路线上，调整工作持续时间","本题考查的是施工进度的动态分析与调整。选项A，把检查当前日期作为剩余网络计划的开始日期；选项C，若产生负时差，则说明项目进度拖后选项D，应在出现负时差的工作路线上，调整工作持续时间，消除负时差，以保证工期按期实现。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]