[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106880":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106880,782,1,"单选题","下列选项不属于工作历时估算方法的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织者预估",true,{"key":16,"text":17,"correct":18},"B","参数估算",false,{"key":20,"text":21,"correct":18},"C","类比估算",{"key":23,"text":24,"correct":18},"D","三点估算","在工作项目的工程量一定的情况下，工作持续时间与安排在工作上的设备水平、人员技术水平、人员与设备数量、效率等有关。在现阶段，工作项目持续时间的确定方法主要有下述几种：①参数估算。参数估算指按实物工程量和定额标准计算。若已有各结构物的设计图纸，就应根据设计图纸，并考虑工程分期、分层、分段等因素，分别计算出相应的工程量；②类比估算。类比估算是一种使用相似工作或项目的历史数据，来估算当前工作或项目的持续时间或成本的技术。类比估算以过去类似项目的参数值（如持续时间、预算、规模、复杂性等）为基础，来估算未来项目的同类参数或指标；③三点估算。通过考虑估算中的不确定性和风险，可以提高持续时间估算的准确性。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]