[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106878":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106878,782,1,"单选题","承包人应按技术标准和要求（合同技术条款）约定的内容和期限以及监理人的指示，编制详细的施工总进度计划及其说明提交（ ）审批。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":18},"B","监理人",true,{"key":20,"text":21,"correct":14},"C","管理层",{"key":23,"text":24,"correct":14},"D","项目负责人","根据《水利水电工程标准施工招标文件（2009年版）》，承包人应按技术标准和要求（合同技术条款）约定的内容和期限以及监理人的指示，编制详细的施工总进度计划及其说明提交监理人审批。监理人应在技术标准和要求（合同技术条款）约定的期限内批复承包人，否则该进度计划视为已得到批准。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]