[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106877":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106877,782,1,"单选题","引水工程通常包含多种工程形式，下列不属于其工程形式的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","疏浚",true,{"key":16,"text":17,"correct":18},"B","渠道",false,{"key":20,"text":21,"correct":18},"C","隧洞",{"key":23,"text":24,"correct":18},"D","倒虹吸","本题考查的是发包人控制性进度计划的编制。引水工程通常包含多种工程形式，如渠道、隧洞、倒虹吸、渡槽等",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]