[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106875":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106875,782,1,"单选题","资源优化主要有（ ）问题。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","资源有限—工期最优的优化",false,{"key":16,"text":17,"correct":18},"B","工期固定--资源均衡的优化",true,{"key":20,"text":21,"correct":14},"C","最小优化",{"key":23,"text":24,"correct":14},"D","费用优化","本题考查的是网络计划优化。资源优化有两类问题：（1）资源有限，工期最短的优化；（2）工期固定，资源均衡的优化。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]