[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106874":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106874,782,1,"单选题","只有紧前工作完成，紧后工作才能完成的逻辑关系属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","STS",false,{"key":16,"text":17,"correct":14},"B","FTS",{"key":19,"text":20,"correct":21},"C","FTF",true,{"key":23,"text":24,"correct":14},"D","STF","本题考查的是网络计划编制。完成到完成（FTF）。只有紧前工作完成，紧后工作才能完成的逻辑关系。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]