[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106873":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106873,782,1,"单选题","在施工进度计划审批中，应仔细分析进度计划与（ ）的协调性。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量控制",false,{"key":16,"text":17,"correct":18},"B","资源计划",true,{"key":20,"text":21,"correct":14},"C","合同工期",{"key":23,"text":24,"correct":14},"D","施工方案","本题考查的是合同性进度计划编制。在施工进度计划审批中，应仔细分析进度计划与资源计划的协调性。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]