[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106872":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106872,782,1,"单选题","施工进度计划应满足合同工期和（ ）的要求。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总体规划",false,{"key":16,"text":17,"correct":18},"B","阶段性目标",true,{"key":20,"text":21,"correct":14},"C","配套资源计划",{"key":23,"text":24,"correct":14},"D","施工方案","本题考查的是合同性进度计划编制。施工进度计划应满足合同工期和阶段性目标（或称进度里程碑）的要求。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]