[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106871":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106871,782,1,"单选题","下列不属于承包人在按照合同要求编制的进度计划时应当满则的要求是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同工期",false,{"key":16,"text":17,"correct":14},"B","进度里程碑目标要求",{"key":19,"text":20,"correct":21},"C","施工场地",true,{"key":23,"text":24,"correct":14},"D","合同其他要求","本题考查的是合同性进度计划编制。承包人在按照合同要求编制的进度计划，首先应当满足合同工期、进度里程碑目标要求和合同其他要求。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]