[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106868":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106868,782,1,"单选题","发包人的（ ）是发包人对项目的建设在时间上和空间上进行全局安排、统一协调的计划。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程测算",false,{"key":16,"text":17,"correct":18},"B","总体控制性进度计划",true,{"key":20,"text":21,"correct":14},"C","工程概算",{"key":23,"text":24,"correct":14},"D","目标计划","本题考查的是发包人控制性进度计划的编制。发包人的总体控制性进度计划是发包人对项目的建设在时间上和空间上进行全局安排、统一协调的计划。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]