[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106867":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106867,782,1,"单选题","当所有工序都采用最短时间时，对应的工期费用说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期最短",true,{"key":16,"text":17,"correct":18},"B","工期最优",false,{"key":20,"text":21,"correct":18},"C","工程直接费用最低",{"key":23,"text":24,"correct":18},"D","工程直接费用最优","本题考查的是网络计划优化。当所有工序都采用最短时间时，此时工期最短，但工程直接费用却是最高的。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]