[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106864":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106864,782,1,"单选题","费用优化又叫时间成本优化，它的目的之一是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","寻求最低成本时的工期安排",true,{"key":16,"text":17,"correct":18},"B","寻求工程成本最少的计划安排",false,{"key":20,"text":21,"correct":18},"C","寻求工期最短的计划安排",{"key":23,"text":24,"correct":18},"D","寻求资源需用量尽可能少的计划安排","费用优化方法，就是以正常费用为初始方案，通过逐步压缩，找出不同工期下的最低直接费用方案。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]