[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106863":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106863,782,1,"单选题","以下关于工作分解结构（WBS）的说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作分解越详细越好",false,{"key":16,"text":17,"correct":14},"B","施工单位应该独立的进行工作分解",{"key":19,"text":20,"correct":21},"C","WBS可以按项目形成过程的阶段进行分解",true,{"key":23,"text":24,"correct":14},"D","工作分解由监理单位组织","WBS 的结构形式通常有两种：一种是按项目形成过程的阶段进行分解；另一种是按照工程组成进行分解。过细的分解会造成管理资源的无效消耗、资源使用效率低下、工作实施效率降低，同时造成WBS 各层级的数据汇总困难。施工单位的工作分解结构一般应该与建设的一致。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]