[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106862":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106862,782,1,"单选题","自始至终全部由关键工作组成的线路为关键线路，或线路上总的工作持续时间（ ）的线路为关键线路。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最短",false,{"key":16,"text":17,"correct":18},"B","最长",true,{"key":20,"text":21,"correct":14},"C","相等",{"key":23,"text":24,"correct":14},"D","以上答案均不对","总时差最小的工作为关键工作。特别地，当网络计划的计划工期等于计算工期时，总时差为0的工作就是关键工作。自始至终全部由关键工作组成的路线或路线上总的工作持续时间最长的路线为关键路线。关键路线在网络图上应用粗线、双线或彩色线标注。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]