[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106859":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106859,782,1,"单选题","下列关于客观估计时间to、最可能估计时间tm和悲观估计时间to之间的关系说的错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当to和tp越远离tm值，方差越大，概率分布越集中",true,{"key":16,"text":17,"correct":18},"B","当to和tp越接近tm值，肯定程度越高",false,{"key":20,"text":21,"correct":18},"C","在极端情况下，当三者相同时，方差为0",{"key":23,"text":24,"correct":18},"D","当to和tp越远离tm值，不确定性越大","本题考查的是计划评审技术（PERT）。，当to、tp越远离tm值，V越大，概率分布越离散，不确定性越大；to、tp越接近tm值，肯定程度越高。在极端情况下，当相同时，Vt为0，与关键路线法中相同，工作历时为一确定值。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]