[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106858":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106858,782,1,"单选题","某分部工程单代号搭接网络计划如下图所示，其中关键工作是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作A和工作B",false,{"key":16,"text":17,"correct":14},"B","工作B和工作D",{"key":19,"text":20,"correct":14},"C","工作C和工作E",{"key":22,"text":23,"correct":24},"D","工作C和工作D",true,"本题考查的是搭接网络计划方法。单代号搭接网络计划可以利用相邻两项工作之间的时间间隔来判定关键线路。即从网络的起点到终点均为关键工作，且所有工作的时间间隔均为零的路线为关键路线。本题需要虚拟一项开始工作S，关键线路为S→C→D→F。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]