[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106857":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106857,782,1,"单选题","在单代号搭接网络图中，工作G的持续时间为4天，紧前工作有 D、E工作。工作D→G之间的搭接关系为STF=12天，工作E→G之间的搭接关系为STS=6天， D、E工作的时间参数如下图所示，则G工作的最早开始时间为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","12天",false,{"key":16,"text":17,"correct":14},"B","14天",{"key":19,"text":20,"correct":21},"C","16天",true,{"key":23,"text":24,"correct":14},"D","18天","本题考查的是搭接网络计划方法。搭接网络图中各种搭接关系的含义：STF为开始到结束的时间间隔；STS为开始到开始的时间间隔。由D和G的关系可知，G最早开始时间为6+12-4=14天；由E和G的关系可知G的最早开始时间为10+6=16天，所以二者取大为16天。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]