[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106856":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106856,782,1,"单选题","根据下列新横道图，计算各工作的时间参数，下列选项错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作2-5的自由时差为1",false,{"key":16,"text":17,"correct":14},"B","工作2-3为虚工作",{"key":19,"text":20,"correct":21},"C","工作3-4的最迟开始时间为5月7日末",true,{"key":23,"text":24,"correct":14},"D","工作5-6是关键工作","本题考查的是双代号时标网络计划及新横道图。选项C错误，工作3-4的最迟开始时间等于最终开始时间加上其总时差，应该为5月8日末。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]