[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106855":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106855,782,1,"单选题","某工程双代号时标网络计划如下图所示，其中工作H的总时差和自由时差（ ）周。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","均为1",false,{"key":16,"text":17,"correct":14},"B","分别为3和0",{"key":19,"text":20,"correct":21},"C","分别为3和2",true,{"key":23,"text":24,"correct":14},"D","均为0","本题考查的是双代号时标网络计划及新横道图。当工作之后只紧接虚工作时，则该工作箭线上一定不存在波形线，而其紧接的虚箭线中波形线水平投影长度的最短者为该工作的自由时差。H工作自由时差为2周，H工作总时差=min{1+2，3}=3（周）",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]