[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106854":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106854,782,1,"单选题","某分部工程双代号时标网络计划如下图所示，其中工作C和I的最迟完成时间分别为第（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4和11",false,{"key":16,"text":17,"correct":18},"B","4和9",true,{"key":20,"text":21,"correct":14},"C","3和11",{"key":23,"text":24,"correct":14},"D","3和9","本题考查的是双代号时标网络计划及新横道图。首先找出关键工作A、D、H、M。工作C和I的总时差分别为2天和1天，所以它们的最迟完成时间分别为4天和9天",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]