[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106853":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106853,782,1,"单选题","下列关于双代号时标网络计划一般规定说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以水平时间坐标为尺度表示工作时间",false,{"key":16,"text":17,"correct":18},"B","当工作有总时差时，用波形表示",true,{"key":20,"text":21,"correct":14},"C","节点中心必须对准相应的时标位置",{"key":23,"text":24,"correct":14},"D","宜按最早时间编制","本题考查的是双代号时标网络计划及新横道图。选项B错误，以波形线表示工作的自由时差。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]