[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106852":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106852,782,1,"单选题","单代号网络计划，非终点节点的工作的总时差等于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","本工作与紧前工作时间间隔加该紧前工作的总时差之和的最大值",false,{"key":16,"text":17,"correct":14},"B","本工作与紧后工作时间间隔加该紧后工作的总时差之和的最大值",{"key":19,"text":20,"correct":14},"C","本工作与紧前工作时间间隔加该紧前工作的总时差之和的最小值",{"key":22,"text":23,"correct":24},"D","本工作与紧后工作时间间隔加该紧后工作的总时差之和的最小值",true,"本题考查的是关键路线法（CPM）。若工作i有唯一的紧后工作j，则其总时差为i与j之间的时间间隔与工作j的总时差之和；若工作i有多个紧后工作，则按上述分别计算，所得和值的最小值为工作i的总时差",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]