[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106850":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106850,782,1,"单选题","某工程双代号网络计划如下图所示，其中关键线路有（ ）条",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","2",false,{"key":20,"text":21,"correct":18},"C","3",{"key":23,"text":24,"correct":18},"D","4","本题考查的是关键路线法（CPM）。关键线路有1条：①→②→③→④→⑥→⑦→⑧。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]