[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106849":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106849,782,1,"单选题","在工程网络计划中，H工作的最早开始时间为第15天，其持续时间为4天，该工作有3项紧后工作，它们的最早开始时间分别为第20天、第22天，第24天，则H工作的自由时差为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","2",false,{"key":20,"text":21,"correct":18},"C","3",{"key":23,"text":24,"correct":18},"D","4","本题考查的是关键路线法（CPM）。根据公式FFi－j＝min{ESj－k－EFi－j}＝min{ESj－k－ESi－j－Di－j}＝min{20－（15＋4），22－（15＋4），24－（15＋4）}＝min{1，3，5}＝1（天）。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]