[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106847":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106847,782,1,"单选题","在双代号网络计划的时间参数计算中，除以网络计划终点节点为完成节点的工作外，其他工作的最迟完成时间应等于其紧后工作（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最迟开始时间的最小值",true,{"key":16,"text":17,"correct":18},"B","最迟开始时间的最大值",false,{"key":20,"text":21,"correct":18},"C","最迟完成时间的最小值",{"key":23,"text":24,"correct":18},"D","最迟完成时间的最大值","本题考查的是关键路线法（CPM）。其他工作的最迟完成时间应等于其紧后工作最迟开始时间的最小值。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]