[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106844":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106844,782,1,"单选题","在某工程双代号网络计划中，工作N的最早开始时间和最迟开始时间分别为第20天和第25天，其持续时间为9天。该工作有两项紧后工作，它们的最早开始时间分别为第32天和第34天，则工作N的总时差和自由时差分别为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3和0",false,{"key":16,"text":17,"correct":14},"B","3和2",{"key":19,"text":20,"correct":14},"C","5和0",{"key":22,"text":23,"correct":24},"D","5和3",true,"本题考查的是关键路线法（CPM）。TFN＝LSN－ESN＝25－20＝5（天），自由时差为紧后工作的最早开始时间减去本工作的最早完成时间之差的最小值，工作N的最早完成时间为第29天，所以自由时差为min{32－29，34－29}＝3（天）",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]