[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106843,782,1,"单选题","A工作后有紧后工作 B、 C，它们的持续时间分别为5d、4d和6d；BC工作最迟完成时间分别为25d和23d，则A工作的最迟开始时间为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4d",false,{"key":16,"text":17,"correct":14},"B","8d",{"key":19,"text":20,"correct":21},"C","12d",true,{"key":23,"text":24,"correct":14},"D","16d","本题考查的是关键路线法（CPM）。A工作的最迟开始时间等于其紧后工作最迟开始时间的最小值减去自身的持续时间=min{25-4，23-6}-5=12（天）",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]