[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106842,782,1,"单选题","计划评审技术中工作的持续时间可以利用三点估算法进行，下列不属于三点估算法估计完成时间的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","客观估计时间",true,{"key":16,"text":17,"correct":18},"B","最可能估计时间",false,{"key":20,"text":21,"correct":18},"C","乐观估计时间",{"key":23,"text":24,"correct":18},"D","悲观估计时间","本题考查的是计划评审技术（PERT）。所谓工作历时的三点估算法，就是在项目已有勘查、观测、试验资料基础上，参照过去实践经验，客观地估计出下列三种情况下的可能完成时间：（1）乐观估计时间；（2）悲观估计时间；（3）最可能估计时间。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]