[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106841":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106841,782,1,"单选题","某分部工程由 A、B工作组成，其中A工作结束4天后，B工作才能开始，则 A、B工作之间的搭接关系是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","从开始到结束",false,{"key":16,"text":17,"correct":14},"B","从结束到结束",{"key":19,"text":20,"correct":21},"C","从结束到开始",true,{"key":23,"text":24,"correct":14},"D","从开始到开始","本题考查的是搭接网络计划方法。A工作结束4天后B工作开始，也就是FTS的关系，是从结束到开始。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]