[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106840":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106840,782,1,"单选题","下列关于有限网络计划计算原则错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作的强制最迟完成时限对工作的最早时间计算没有影响",false,{"key":16,"text":17,"correct":18},"B","计划工期要同时满足工期和时限的要求并取其中的大值",true,{"key":20,"text":21,"correct":14},"C","工作的强制最早开始时限对工作的最迟时间工作没有影响",{"key":23,"text":24,"correct":14},"D","工作的总时差计算与普通网络图中的计算相同","本题考查的是有时限的网络计划。网络计划的计划工期要同时满足工期和时限的要求并取其中的小值。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]