[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106839":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106839,782,1,"单选题","由于某原因规定了某项工作不得早于某时刻开始，这类网络计划属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","双代号网络计划",false,{"key":16,"text":17,"correct":14},"B","双代号搭接网络计划",{"key":19,"text":20,"correct":21},"C","有时限的网络计划",true,{"key":23,"text":24,"correct":14},"D","单代号网络计划","本题考查的是有时限的网络计划。网络计划中的工作，除了受逻辑关系约束而不能违反既定顺序关系之外，有的还由于外界因素的影响而在时间安排上受到某种限制：或不得早于某时刻开始；或不得迟于某时刻完成；或不得安排在某一期间进行。这就是最早开始时限、最迟完成时限和中断时限，统称为时限或强制时限",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]