[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106838":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106838,782,1,"单选题","某工程双代号时标网络计划如下图所示，其中工作B的总时差和自由时差（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","均为2周",true,{"key":16,"text":17,"correct":18},"B","分别为2周和3周",false,{"key":20,"text":21,"correct":18},"C","均为3周",{"key":23,"text":24,"correct":18},"D","分别为3周和2周","本题考查的是双代号时标网络计划及新横道图。工作H的总时差为1周，工作I的总时差为3周，工作J的总时差为0周，则工作E的总时差为0周，所以工作B的总时差为0＋2＝2（周）。B工作的自由时差为该工作箭线中波形线的水平投影长度，即为2周。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]