[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106836":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106836,782,1,"单选题","下列关于时标网络计划的间接绘制法的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","需要先根据无时标的网络计划草图计算各节点的最早时间",false,{"key":16,"text":17,"correct":18},"B","在绘制时应先将所有节点按其最迟时间定位在时标网络计划表中的相应位置",true,{"key":20,"text":21,"correct":14},"C","当某些工作箭线的长度不足以到达该工作的完成节点时，须用波形线补足",{"key":23,"text":24,"correct":14},"D","自左至右确定各节点的位置","本题考查的是双代号时标网络计划及新横道图。选项B错误，间接绘制法，是指先根据无时标网络计划草图计算各节点的最早时间，然后将各节点按其最早时间定位在时标网络计划表中的相应位置。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]