[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106831":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106831,782,1,"单选题","某单代号网络图，有多项开始工作和结束工作，则该网络图（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","起点节点为实工作，终点节点为实工作",false,{"key":16,"text":17,"correct":14},"B","起点节点为实工作，终点节点为虚拟工作",{"key":19,"text":20,"correct":14},"C","起点节点为虚拟工作，终点节点为实工作",{"key":22,"text":23,"correct":24},"D","起点节点为虚拟工作，终点节点为虚拟工作",true,"本题考查的是网络计划技术基础知识。单代号网络图只应有一个起点节点和一个终点节点；当网络图中有多项起点节点或多项终点节点时，应在网络图的两端分别设置一项虚工作，作为该网络图的起点节点和终点节点。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]