[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106827":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106827,782,1,"单选题","经济净现值是指将项目在整个计算期内各年（ ）用社会折现率折算到建设期初的现值之和。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","现金流量",false,{"key":16,"text":17,"correct":14},"B","效益流量",{"key":19,"text":20,"correct":14},"C","净现金流量",{"key":22,"text":23,"correct":24},"D","经济净效益流量",true,"经济净现值是指将项目在整个计算期内各年经济净效益流量用社会折现率折算到建设期初的现值之和。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]