[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106825":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106825,782,1,"单选题","某工作最短估计时间是5 天,最长估计时间是10 天,最可能估计时间是6 天。根据三时估算法,该工作的持续时间是( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6.25",false,{"key":16,"text":17,"correct":18},"B","6.5",true,{"key":20,"text":21,"correct":14},"C","6.75",{"key":23,"text":24,"correct":14},"D","7","",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]