[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106824":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106824,782,1,"单选题","在某工程单代号搭接网络计划中，关键线路是指（ ）的线路。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","相邻两项工作之间的时距之和最大",false,{"key":16,"text":17,"correct":18},"B","相邻两项工作之间的时间间隔全部为零",true,{"key":20,"text":21,"correct":14},"C","工作的持续时间总和最大",{"key":23,"text":24,"correct":14},"D","相邻两项工作之间的时距全部为零","单代号搭接网络计划中，总时差最小的工作为关键工作。从网络的起点到终点均为关键工作，且所有工作的时间间隔均为零的路线为关键路线。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]