[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106815":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106815,782,1,"单选题","下列工程进度曲线表示的是（ ）曲线。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","累计完成量",false,{"key":16,"text":17,"correct":14},"B","每天完成工程量",{"key":19,"text":20,"correct":14},"C","每天完成相同数量的施工进度",{"key":22,"text":23,"correct":24},"D","每天完成不同数量的施工进度",true,"本题考查的是进度计划的表示方法。在施工初期由于施工准备、施工临时设施、工作面较少等原因，施工后期由于工程收尾、验收等原因，施工速度一般较施工高峰期要慢。每天的完成数量通常自初期至中期呈递增趋势，由中期至末期呈递减趋势。施工进度曲线一般呈S形。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]