[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106814":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106814,782,1,"单选题","下列关于横道图表示建设工程进度计划的特点说法不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","能够明确表示各项工作的开始时间",false,{"key":16,"text":17,"correct":14},"B","一目了然.易于理解",{"key":19,"text":20,"correct":21},"C","能够反映各项工作之间的相互关系",true,{"key":23,"text":24,"correct":14},"D","不能反映各项工作的机动时间","本题考查的是进度计划的表示方法。选项C错误，不能明确地反映出各项工作之间的相互关系。在计划执行过程中，某些工作的进度提前或拖延时，不便于分析其对其他工作及总工期的影响程度。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]