[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106812":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106812,782,1,"单选题","发包人的总体控制性进度计划主要包括工程项目建设总进度计划和（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计单位实施进度计划",false,{"key":16,"text":17,"correct":14},"B","承包人实施进度计划",{"key":19,"text":20,"correct":14},"C","设备采购单位实施进度计划",{"key":22,"text":23,"correct":24},"D","工程项目年度进度计划",true,"本题考查的是建设项目进度控制概述。发包人的总体控制性进度计划主要包括工程项目建设总进度计划、工程项目年度进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]