[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106811":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106811,782,1,"单选题","利用横道图表示工程进度计划的主要特点是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","能够反映工作所具有的机动时间",false,{"key":16,"text":17,"correct":14},"B","能够明确表达各项工作之间的逻辑关系",{"key":19,"text":20,"correct":21},"C","形象直观，易于编制和理解",true,{"key":23,"text":24,"correct":14},"D","能方便地利用计算机进行计算和优化","优点：（1）能明确地表示出各项工作的开始时间、结束时间和持续时间。（2）一目了然，易于理解，能够为各层次的人员所掌握和运用。缺点：（1）不能明确地反映出各项工作之间的相互关系。（2）不能明确地反映出影响工期的关键工作和关键路线，不便于进度控制人员抓住主要矛盾。（3）不能反映出各项工作所具有的机动时间，这不便于施工进度管理和资源调配。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]