[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106806":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106806,782,1,"单选题","待摊投资的分摊对象不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","房屋、建筑物",false,{"key":16,"text":17,"correct":14},"B","需要安装的通用设备",{"key":19,"text":20,"correct":21},"C","需要安装的专用设备",true,{"key":23,"text":24,"correct":14},"D","水、电专用设备","待摊投资的分摊对象应为以下几项内容：①房屋、建筑物；②水、电专用设备；③需要安装的通用设备；④其他分摊对象等。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]